How many GORE® Modules can be installed in a typical day for soil gas sampling?
Under ideal conditions, two (or three) experienced field technicians can install 50 to 70 or more GORE® Modules during a regular workday (this assumes the sample grid has been established prior to the installation, and no significant obstacles are encountered in the field). Typically, one person drills the installation holes, while the second person installs the modules and maintains the field notes, maps, and installation log.