Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How long would the reservoir take to build?

build reservoir
0
Posted

How long would the reservoir take to build?

0

Construction time would be dependent on the size of the reservoir. A reservoir of 150 million cubic metres would take approximately eight years to build (and up to a further two to fill it), while a reservoir with a capacity of 100 million cubic metres would take about a year less overall.