Beginning in January, the West Plaza asphalt will be removed, followed by several weeks of utility work to provide site drainage and power to the new light poles. After the utility work is complete, new granite curbs, concrete foundations and asphalt pavers will be installed similar to the North Plaza. The Greenmarket will relocate to the South Plaza while Phase Two construction work is underway. All work on the West Plaza should be complete by April 2009.