Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How long will the Port Phillip Bay channel dredging take and when will it start?

Bay channel dredging Phillip port
0
Posted

How long will the Port Phillip Bay channel dredging take and when will it start?

0

With dredging to commence on 7 February 2008, it is expected to be completed by January 2010. As from the commencement of dredging, the Port of Melbourne Corporation will hold a Project News Conference each morning at 10 am (Monday-Friday) at the Port of Melbourne Corporation HQs, Level 4, 530 Collins Street, Melbourne to advise on dredging activities from the previous 24 hours and planned activities the next 24 hours.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123