Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How long will it take to receive an acceptance letter for my solar project once the NJCEP receives my SRP registration package?

0
Posted

How long will it take to receive an acceptance letter for my solar project once the NJCEP receives my SRP registration package?

0

As long as the SRP package is complete, it typically takes about 5 to 7 weeks. Incomplete registrations are returned to the host site contact. Once a registration is reviewed by the processing team, it will be data entered into the registration system. You can also review the Program Status Reports to see your project status.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123