Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How long will it take to build CAD Analyst and Fire/EMS ADAM for my department?

0
Posted

How long will it take to build CAD Analyst and Fire/EMS ADAM for my department?

0

Phase I: Obtaining and processing raw data into a form needed by CAD Analyst Will be completed within 30 days of project initiation. Manpower needed: One (1) Department analyst needed for a maximum of 15 hours for annotating the grids with hazard type and descriptions Phase II: CAD Analyst Will be completed within 30 days after Phase I. Manpower needed: One (1) Department analyst needed for a maximum of 10 hours to assist Deccan over the phone in analysis validation Phases III Fire/EMS ADAM Will be completed within 30 days after Phase II.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123