How long does the rezoning process take?
The rezoning process, conditional use review process and planned development review process take a minimum of four and a half (4 ) months. Applications are submitted on the third Wednesday of the month and are heard by the DRC on the fourth Wednesday of the following month. Applications certified by the DRC, are advertised the next month, and are heard by the Zoning Commission the first Thursday and the Board of County Commissioners the fourth Thursday of the following month.