How long does it take to remodel a kitchen (on an average)?
Usually it takes 2 to 3 months dependent on kitchen size and details involved in the project. The first step is to take measurements. We then supply the customer with a 3 dimentional sketch so they will be able to better envision their future kitchen. We also provide a sample of the cabinet door, with the wood color and style that the customer had chosen. After appoval we move on with the process. Building custom cabinets can take 4 to 8 weeks (depending on the size and the amount of detail in the kitchen), we then install the custom cabinets, floors, countertops, plumbing, electrical which can take another 4 to 6 weeks.