How long does it take to remediate a site using ET-DSP™?
(Top) In general, target temperatures are achieved within 60 days of commencement of heating. Notwithstanding unique contamination challenges, the heating process of ET-DSP™ generally runs its course within a time frame between 3 to 12 months. Installation and operations commissioning of ET-DSP™ system components typically requires 2 to 6 weeks. At the end of the day, a site cleaned using ET-DSP™ is ready for re-utilization in a matter of months, not years.