Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How long does it take to process a BGA component average package using the SolderQuik BGA Solder Preforms?

0
10 Posted

How long does it take to process a BGA component average package using the SolderQuik BGA Solder Preforms?

0
10

The actual labor time to reball a properly prepared component is roughly 30 seconds per package, plus four or five minutes of reflow time. Multiple packages can be placed through reflow at one time.