Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How long does it take to obtain a permit to install an on-site sewage system?

0
Posted

How long does it take to obtain a permit to install an on-site sewage system?

0

A. For a conventional system, you should allow two to three weeks after the on-site investigation is performed. Professionally designed systems can take four to five weeks after the date of the on-site investigation for the permit to be issued.