How long does it take to install a Propane / Air standby system?
Smaller prepackaged units can be totally installed in as little as one to three days. Larger units that consist of 30,000-gallon tanks may take up to four or five weeks to install. In addition to the installation, it usually takes about 10-12 weeks for the manufacturing of the vaporizer and mixing equipment. We normally allot 12-16 weeks for the cycle: from purchase order to installation and training to be completed.