How long does it take to have plats approved?
The procedure for minor subdivision, addition and/or sewage reserve area relocation plats take 12 weeks on average from submittal to recordation. The plats are routed to various different agencies for comments and approvals which must be obtained prior to recording the plats. The 12 weeks includes the time waiting for responses from the different agencies and revisions from surveyors, however this process can be shorter or longer.