How long does it take to get a Conditional Use Permit or Variance approved?
A. It will take 6 weeks. Due to advertising deadlines we must have your application into the Planning Department on or before the third Wednesday of the month to be placed on the following month agenda. The Planning Commission meets the second Tuesday of the month and the City Council meets on the fourth Tuesday of the month to discuss and act on the Planning Commission recommendations.