How long does it take to complete the Stencil Systems process?
This varies, depending on the preparation and technique required. Normally, the process can be completed in 2 to 3 days. The first day includes the site preparation and form work. The following day or days is for pouring the concrete, applying the stencil pattern and color hardener, cleaning and sealing the finished job. However, as concrete does not reach full strength for 28 days, it is recommended that you allow at least 2 days before walking on the new concrete surfaces and allow a minimum of 7 days for vehicular traffic, depending on weather conditions.