How long does it take to complete the Stencil Pattern Concrete process?
This varies, depending on the preparation required. Normally the process can be achieved in 3 days. The first day includes form work and site preparation. Day 2 is pouring the concrete and applying the colour hardener and stencil pattern and the final day is cleaning up and sealing the finished job. However, as concrete does not reach full strength for 28 days, it is recommended that you allow at least 7 days before you use the new concrete surface.