How long does it take to complete a polished or stamped concrete floor?
A. The timetable for the typical 2000 sq.ft. – 5000 sq.ft. project, with 3-5 men: Day 1 – Mask, Sand, Wash, Rinse, Patch, Prime Day 2 – Prime and install Concrete Topping Day 3 – Basic Secondary Coloration e.g. Patina Etch Stain, or concrete dying – and first coat of Sealer if time permits. Day 4 – Second coat of Sealer and two coats of Deco Finish More time will be required for speciality custom concrete flooring work. Note: Smaller projects have about the same time schedule.