How long does it take to complete a modular home in the factory?
The average modular home takes approx. 5 days to build. This can depend on the size and complexity. It takes another day or so to wrap and make the modular home ready for transport with all the loose materials packaged needed to complete the house. A more important question to be asked of the factory is how long will it take to get my modular home in production. Once the home is delivered to the site the modules need to be placed and/or erected by a crane on its foundation. Final completion can be by a modular dealer who is a local builder or a general contractor hired by the owner. The owner can act as the general contractor if he/she has the time and the acquired expertise. The general contractor hires the subcontractors that handle all the scheduled finish and site work. This consists of making connections from the utilities to the home and a list of site finish work. This can be completed in six to eight weeks and depends on the amount of work necessary to finish the job. The compl