How long does it take to build a plant, from the permit phase to the final construction phase?
The time required for full implementation of a desalination plant varies from project to project. Obviously, it depends on the size and complexity of the plant, and whether it has to be built from scratch or can use existing water intake structures. As an example, planning for the 27.5-MGD El Paso-Fort Bliss brackish groundwater desalination plant started in 2001, a draft Environmental Impact Statement was completed in July 2004, construction of the plant commenced in early spring 2005, and it was opened in August 2007.