How long does it take for Planning Commission and City Council to act on a rezoning or special use permit request?
• 2 – 2.5 months. Both rezonings and special use permits are first considered by Planning Commission and then are forwarded on to City Council for their consideration the following month. City Council will decide if the request is granted. Rezonings are required to have a second reading at City Council, this adds two weeks to the process.