Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How long did it take to build the dam, powerplant, and appurtenant works?

0
Posted

How long did it take to build the dam, powerplant, and appurtenant works?

0

Five years. The contractors were allowed seven years from April 20, 1931, but concrete placement in the dam was completed May 29, 1935, and all features were completed by March 1, 1936.

0

Five years. The contractors were allowed 7 years from April 20, 1931, but concrete placement in the dam was completed May 29, 1935, and all features were completed by March 1, 1936.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123