Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How long after a Public Hearing does the DEQ have to grant or deny a permit?

deny deq hearing permit public
0
Posted

How long after a Public Hearing does the DEQ have to grant or deny a permit?

0

If a public hearing is held under Part 301 the MDEQ has 120 days from when the file was determined to be administratively complete to make a decision to grant or deny a permit. If a public hearing is held under Part 303 or Part 325, the MDEQ has 150 days from when the file was determined to be administratively complete to make a decision to grant or deny a permit. 16.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123