How far in advance should I schedule a Slab, Rough-in or Trim?
Generally we will need three days notice to schedule a Slab and Five days to schedule a Rough-in or Trim. (These time frames allow sufficient time to schedule the necessary crews and order material, as well as verify any specification changes.) By allowing this time frame we can ensure that costly delays caused by return trips to jobs are minimized.