Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How does tracking in RiskyProject work?

riskyproject
0
Posted

How does tracking in RiskyProject work?

0

You can enter a percent of task completion on a certain day. RiskyProject uses this information to calculate a forecasted task duration which takes into account risks and task progress. The actual chance of risk occurrence is automatically updated. You can easily compare the results of tracking with the original (baseline) project schedule.