How does the zoning process work?
First, you submit the completed permit application form (with necessary drawing), along with the required fee. The Zoning Administrator has 30 days to act on a permit, although it is usually addressed within 1-2 weeks. After the Zoning Administrator approves the permit, it is posted at the Wallingford Post Office and Town Hall for 15 days, during which interested parties may file an appeal. If the permit is not appealed, then construction can begin after the 15 day waiting period.