Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How does the software view the energy bid blocks when a unit is Self Schedule Regulation?

0
Posted

How does the software view the energy bid blocks when a unit is Self Schedule Regulation?

0

When a generator has requested to be Self-Scheduled for regulation, its ranking price, except for a tiebreaker, is zero. Energy bid blocks are not considered at all in the ranking, because a Self-Scheduled for regulation generator will not get paid opportunity cost. So if you are requesting a Self-Scheduled for generation status, you’ll be accepted for it unless there are transmission or other reliability concerns, of its larger Self-Scheduled for regulation generators have met the full requirements. Note: that your regulation bid, when Self-Scheduled for regulation, is treated as a zero regulation bid.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123