Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How does the Fire Marshals Office determine the required fire-flow for my project?

0
Posted

How does the Fire Marshals Office determine the required fire-flow for my project?

0

The fire-flow requirement is determined using the gross square footage and California Building Code construction type as indicated by Table B105.1 of the 2007 County Fire Code.