How does the design approval process work?
• IPO agrees scope of work with the School Principal • IPO issues scope of work to Federal Government for approval • Federal Government approves scope of work • IPO issues project brief to Managing Contractor (MC) • MC undertakes site investigation and prepares schematic design based on agreed scope of work • MC issues schematic design to the IPO for approval • IPO approves schematic design • MC prepares detailed design • MC issues detailed design to the IPO for approval • IPO approves detailed design • MC prepares final Approved For Construction (AFC) documentation • MC issues final AFC documentation for information