Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How does New Hampshires Alteration of Terrain (Site Specific) permit differ from that of the Phase II Storm Water General Permit for Small Construction Activity?

0
Posted

How does New Hampshires Alteration of Terrain (Site Specific) permit differ from that of the Phase II Storm Water General Permit for Small Construction Activity?

0

New Hampshire’s Alteration of Terrain permit and EPA’s permits differ in coverage based on the size and location of the project. A Alteration of Terrain permit from NHDES is required for any contiguous area of disturbance exceeding 100,000 square feet (approximately 2.3 acres), or 50,000 square feet if the disturbance is partially or wholly located within the protected shoreland. The plans and documents developed for a Alteration of Terrain permit will satisfy many, but not all, of the required components of a Storm Water Pollution Prevention Plan (SWPPP) for the CGP.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123