How does eFT anticipate estimated Delivery Date and delay?
a. eFT benefits from the structured Flow Templates. b. Flow Templates consist of Tasks. Each task has a planned duration and relation with other tasks. For instance, the planned duration for cutting is 2 days and unless cutting is completed its related task `sewing` cannot start. c. If cutting is delayed, eFT recalculates new end and start dates for sewing. If cutting or sewing is on the Critical Path, Estimated Delivery Date will also be suitably amended.