How does an operator demonstrate that an existing LFG monitoring and control system is in compliance with the standards?
The operator would need to submit a system design that demonstrates that the LFG monitoring system is in compliance with the standards. The system could include, but not be limited to: LFG well/probe as-builts, boring logs, plot plans showing well locations/spacing, and any other pertinent evidence. The regulations do not require the development of new information if existing information is available that adequately documents the LFG monitoring system compliance with the standards. Existing information may be located in the JTD or closure/postclosure plans, and could be referenced in the submittal.