Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How do I put AdvanTech flooring on the poured concrete floor in my basement?

0
Posted

How do I put AdvanTech flooring on the poured concrete floor in my basement?

0

There are two methods used to attach AdvanTech panels to concrete slabs. Both methods require the preparation of the slab. Slab Preparation Cover the slab with minimum 4 mil (6 mil preferred) polyethylene sheeting. The polyethylene sheet should be glued to the slab with an adhesive that will bond to both concrete and plastic. All joints in the polyethylene sheeting should be lapped a minimum 4″. These laps should also be glued to ensure an adequate moisture seal. The plastic should extend up sides of the walls a few inches. Once the AdvanTech sheathing is installed, the excess plastic can be trimmed flush. Method 1 – Application direct to slab • It is recommended that a square edge panel be used for this method. • After preparing the slab as described above, place panels directly on polyethylene sheeting. • Space panels 1/8″ at edges and ends. • Fasten panels with masonry nails, concrete fasteners or powder-actuated fasteners. • Place fasteners 3/8″ from panel edges. • Space fasteners

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123