How do I go about filing and enforcing a mechanics or materialman’s lien on real property?
If you have delivered materials to or performed work on real property, you may have a right to file a lien against the property in an effort to ensure that you get paid for the materials or work. The lien must meet statutory requirements, and the lien must be verified. It must be filed in the county records within 90 days of the last materials supplied or work performed, and a copy must be delivered or mailed by certified mail to the owner within five (5) days of filing the lien. A suit to enforce the lien must be filed within six months of the filing of the lien or it will be deemed to have expired. The lien claimant is entitled to recover attorney fees for preparing and filing the lien as well as enforcing it.