Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How can I view the tasks allocated to a particular resource in Gantt Chart?

0
Posted

How can I view the tasks allocated to a particular resource in Gantt Chart?

0

Click the Filter button (or select Filter from Project / Filter menu), chose Using resource. From available filters, click “Apply”, type or select the resource name in the combo box and then click ok. Gantt Chart View will display only the tasks allocated to the selected resource.