Has the Governing Board changed the scope beyond the computing and networking infrastructure? When will there be a “stake in the ground” to finalize scope?
A36. The entire computing and networking infrastructure is in scope unless some portion thereof dilutes the savings of the business case. Other projects may emerge from CNIC, but those projects need to be kept separate. It is intended to finalize scope by the end of Task 7 [of the Accenture contract], however, there may be instances during agency-specific consolidation planning where more things are included in the new data center—or excluded—based on agency need and/or savings generated or diluted.