Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

For a project using the TRCR, does the bidder need to estimate the cost of upgrades needed to bring power to a given cluster, assuming the interconnection point is not the same point as the cluster?

0
Posted

For a project using the TRCR, does the bidder need to estimate the cost of upgrades needed to bring power to a given cluster, assuming the interconnection point is not the same point as the cluster?

0

No, the bid evaluation is based only on the Transmission Ranking Cost from the Clusters. For bid evaluation purposes, PG&E will assume that the cost to bring power to the interconnection point is internalized within the bid.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123