Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

ENGINEERING DIVISION FAQs EXCAVATION PERMIT FOR CONTRACTOR What is required for an Excavation Permit?

0
Posted

ENGINEERING DIVISION FAQs EXCAVATION PERMIT FOR CONTRACTOR What is required for an Excavation Permit?

0

• Complete Excavation Permit Application • Final improvement plans for the work must be submitted (3 sets required) • Traffic Control Plan must be submitted (3 sets required) and approved by Traffic Engineer. Plan review turn-around time is approximately 5 days for each submittal.