Does the Vico Office Suite calculate the duration of the tasks and the production rate automatically from information in the database?
Yes. Vico Office integrates the model and the database and the schedule. The duration is calculated based on the productivity rate from the database, quantities from the 3D model, and the crew size entered or optimized from Vico Office Schedule Planner. Q: Do you have training classes on all that Control has to offer? A: Yes we do and I suggest you start first with the interactive training guide which are free to download form our website. Once you go through the ITG then we have different classes for advanced and expert levels. You can contact us for additional training. Q: Can this schedule Control chart be summarized into a cumulative progress S-curve where we have early, late planned and actual for the project as a whole? A: Yes you can. We have a value analysis view of the project where you can superimpose exactly those metrics and use it together with the model. Q: How does the matrix for updating progress effect the schedule if the task is not entirely completed? Let’s say that