Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Does the Knost Flood Wall™ cost estimate include pilings under the footing?

0
Posted

Does the Knost Flood Wall™ cost estimate include pilings under the footing?

0

A. The need for pilings under the KFW would be determined by the site soil conditions and footing size. In any event, assuming a site where pilings were required to be placed every 10 feet of wall length driven to refusal or 20 ft. deep, the cost impact would be minimal.