Does the general contractor have any responsibility in the MBE Program?
A. Yes. The general contractor must first meet the MBE goals established on the contract by seeking out and utilizing certified MBEs. Once work begins, the general contractor is responsible for all project activities including those of subcontractors. Regular monitoring assures that contractual items are performed in accordance with specifications. Monthly reports must be submitted by the general contractor such as payroll, cost and time estimation and progress reports. When changes are needed, the general contractor must get approval from the agency project manager. Any changes in the MBE participation must be approved.