Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Does the Contractor have to submit every pit for Material Source Approval?

0
Posted

Does the Contractor have to submit every pit for Material Source Approval?

0

The Contractor must present the Project Engineer with a valid (current year) COA for each contractor optioned area to be used on a NDDOT project. If a COA posted on the web does not reflect the current year, contact the Environmental and Transportations Services Division. COAs are available on the NDDOT Material Source Certificate of Approval Website. If a COA is not available for the source, the contractor must submit SFN 58466: NDDOT Material Source Approval Request Form. Be sure to attach a map showing the boundary of the area you intended to be used. Every location that is used on a project must have a COA.

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123