Does OPS expect operators to progress through the four risk analysis methods, from least complicated to most complicated as the operator moves to a performance based program?
No. The four risk assessment approaches described in ASME/ANSI B31.8S are all valid. The approach that is appropriate for an individual operator will often be driven by circumstances specific to that operator, including the size/complexity of their system and the expertise/experience of their personnel. Some operators, particularly those with few miles of transmission pipeline, may conclude that the SME approach is sufficient.