Does maintenance of quarry stone breakwaters and revetments fall under Category I, provided a permit has been issued in the past?
A25. Such a project would be evaluated on a case-by-case basis for qualification under Regional Permit 9 (Maintenance), Category II. Q26. For construction of revetments and breakwaters where a layer of sand is present and the sand needs to be excavated to clay for stability, how does this type of dredging fit into the Regional Permits? A26. Dredging for shoreline protection installation is allowed under Regional Permit 11 (Marine Structures and Activities).
A24. Such a project would be evaluated on a case-by-case basis for qualification under Regional Permit 9 (Maintenance), Category II. Q25. For construction of revetments and breakwaters where a layer of sand is present and the sand needs to be excavated to clay for stability, how does this type of dredging fit into the Regional Permits? A25. Dredging for shoreline protection installation is allowed under Regional Permit 11 (Marine Structures and Activities).