Does HUD always require a contingency reserve to cover unexpected cost increases?
Typically, yes. On properties older than 30 years and over $7,500 in rehabilitation costs, the cost estimate must include a contingency reserve. The reserve must be a minimum of ten (10) percent of the cost of rehabilitation; however, the contingency reserve may not exceed twenty (20) percent where major remodeling is contemplated. If utilities were not turned on for inspection, a minimum fifteen (15) percent is required.