Does ASARECA request for accountability of overhead charges?
It depends on how the overhead charges were agreed upon in the approved budget. If it were agreed on a percentage charge basis, the institution will charge applying that percentage rate on actual project expenditure incurred, but not on the budget figure. If it were agreed on itemized overhead cost elements, then the institution will have to provide evidence of actual expenditure for each itemized overhead cost elements.