Does Agilo for Scrum allow multiple Product Backlogs?
Solution 1: In Agilo you can set up independent (trac) environments for each project, so they all have their own and independent Product Backlog. Solution 2: In case that multiple Product Owner partitioning the work you can use the “component” property of Stories and Requirements to assign a particular portion of the Backlog to a Product Owner. Every Backlog allows you to filter by that component so that every Product Owner can see the whole but also only his portion of the backlog.
Unfortunately, you can only have one Product Backlog per environment. However, there are solutions to track multiple products with Agilo: • Solution 1: You can set up independent (Trac) environments for each project, so they all have their own and independent Product Backlog. • Solution 3: If one team is not working on more than one product, you can enable milestone backlogs and use one or more milestones for each product. Sprint planning would be based on each product’s milestone backlog. The Product Backlog would be used to manage high level items such as Requirements or Minimal Marketable Features. • Solution 3: In case that multiple Product Owners partitioning the work you can use the “component” property of Stories and Requirements to assign a particular portion of the Backlog to a Product Owner. Every Backlog allows you to filter by that component so that every Product Owner can see the whole but also only his portion of the backlog.