Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Do the DoD EVM requirements flow down to subcontractors?

0
Posted

Do the DoD EVM requirements flow down to subcontractors?

0

A. Yes, the EVM requirements flow down to the subcontractor if the subcontract is valued at or greater than $20 million. Subcontractors with contracts valued at or greater than $50 million are subject to the EVMS validation requirement. In accordance with the DFARS clauses, the prime contractor identifies the major subcontractors in its proposal. The government then determines, and specifies by name in the prime contract, which of those major subcontracts must comply with the EVM requirements.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123