Do permits issued before October 1st but modified after October 1st for reasons other than thermal need to be evaluated for thermal limits at the same time as the modification?
If a permit is issued prior to October 1st, but gets modified after October 1st, that permit does not need to be evaluated for thermal limits if the modification is unrelated to thermal. In this case, the thermal limits would be evaluated, as typical, at the time of permit reissuance. It is advantageous, however, for facilities to begin thermal monitoring prior to permit reissuance.