Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Do I still need to wait until 41 days after substantial completion of the entire building to receive my share of the builders lien holdback?

0
Posted

Do I still need to wait until 41 days after substantial completion of the entire building to receive my share of the builders lien holdback?

0

A. No. Under the new multiple holdback system, the general contractor maintains a separate holdback for each subcontract, which will be released 55 days after the payment certifier issues a certificate of completion for that subcontract. Q. I work for a bank. The bank is ready to advance a draw on a construction mortgage, but there are liens filed against the property. The draw is needed to complete the building. How can the bank’s advance have priority over the liens? A. The general rule is that advances made by a lender after a lien is filed do not have priority over the lien. However, it may be possible for the bank to apply the advance to the payment of the liens. The new Act also allows the bank to apply for a court order that the mortgage advance will have priority over the filed liens. The court will make the order if it is satisfied that the advance will be applied to complete the construction and will result in increased value to the property at least equal to the amount of th

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123