Did the Government terminate the contract awarded June 21, 2005, to Kellogg Brown & Root Services, Inc.?
No, the GAO did not recommend termination of this contract while corrective actions were being taken. The GAO recommended that the Government make a new source selection decision based on reevaluating proposals; if at the conclusion of those activities, another offerors proposal represented the best value, at that point the contract with Kellogg Brown & Root Services, Inc. would be terminated. During the period of reevaluation, the contract was placed under a stop-work order.
Related Questions
- It has been my experience that it takes forever to process anything through the government. How long does it take to complete processing a contract with the General Services Administration?
- Why was the June 21, 2005, contract award to Kellogg Brown & Root Services, Inc. protested?
- Why is the contract changing from Palmetto GBA to CIGNA Government Services?